Task Settings
A
Written by Ashok P
Updated over a month ago

You can access the Task Settings in the Control Panel to set your preferences for tasks created in SI.

To access the Task Settings, click the following icon.

task settings.jpg

This will open the following form.

task settings form.jpg

The following are the Task settings.

Setting

Description

Include Miscellaneous Hours in Tasks

This setting determines whether Base and Miscellaneous Sub-Labor Type hours should be included for items added to tasks.

Default = Yes.

Default Task Duration (Hours)

This will set the default duration for tasks created in Task Explorer and for planning tasks in the Gantt View.

Default = 8.00.

Automatically update % Complete based on items marked as installed in Tasks

This will update the % Complete field based on the items marked as "Installed" on tasks relative to the total hours for all items on the task.

This setting will also be applied to tasks published to Mobile Install.

Default = No.